BRIDGES
The SCON organization's Bridge Division is highly skilled in manufacturing, supplying, and installing state-of-the-art bridges. Their expertise includes prestressing systems such as HDPE corrugated sheathing, anchorage cone, and anchorage heads wedges. They also excel in the installation of various bridge bearings, including POT-PTFE bearing, elastomeric bearing, pin metal bearing, and spherical bearing. In addition, they specialize in structural expansion joints such as strip seal, seal, and modular. Their vast range of services includes the supply of prestressing equipment with hydraulic jacks from 5 ton to 1000 ton capacity, hydraulic pump, grouting dund, etc.
01
KHARGHAR SKY WALK CABLE STAY, MUMBAI (2012)
Weight of strands 8 Tons
Main Span-70M+51M
Client Name: City & Industrial Development Corp (CIDCO)
Contractor: J Kumar Infra Projects Ltd.
Design Consultant: Spectrum Techno Consultants Pvt. Ltd. Structural Engineer
02
ZUARI RIVER CABLE STAY, GOA
Weight of strands 1200MT
Main Span - 360M
Client Name: Ministry of Road Transport & Highways, New Delhi, Govt Of India
Contractor: Dilip Buildcon Ltd., Mostobudivelnule Zahin
No (DBL-MBZ(.V.))
Design Consultant: Ingerop Consultant, France Infinite Civil Solutions Pvt Ltd. Multimedia Consultants S.N. Bhobe & Associates
03
MAHATMA MANDIR CABLE STAY GANDHINAGAR, GUJRAT (2016)
-
Weight of strands 15 Tons
-
Main Span-150M+90M
-
Client Name: Government of Gujrat, Road & BuildingDept.
-
Design Consultant Contractor: SPCL & AFCONS
04
MITHAPUR CABLE STAY BRIDGE, PATNA, BIHAR
-
Weight of strands 50 Tons
-
Main Span - 37M+74M+37M
-
Client Name: Bihar Rajya Pul Nirman Nigam Limited,Patna
-
Design Consultant Contractor: Spectrum TechnoConsultants Pvt. Ltd.
-
Contractor: S.P. Singla Construction Pvt. Ltd.
05
GIFT CITY CABLE STAY BRIDGE ,GUJRAT
-
Main Span - 20+41.8+41.8+20 Mtr.
-
Client Name: Gandhinagar Municipal Corporation
-
Contractor : Ajay engineering Infrastructure Pvt.ltd
06
​ VENGURLA PEDESTRAIN CABLE STAYED BRIDGE, VENGURLA, MAHARASTHRA (2022)
-
Weight of strands 3.1 Tons
-
Client Name: Executive Engineer Public Works Division,Sawantwadi Govt of Maharashtra.
-
Design Consultant Contractor: MANOJA STHAPATYA,Pune
-
Contractor: TENSILE MEMBRANE SYSTEMS PUNE Pune
07
Hanogi Cable stayed bridge at Mandi,Himachal (2022)
-
Main Span-95m span cantilever 20m pylon ht.Client Name: HIMACHAL PRADESH P.W.D. (SERAJDIVISION)
-
Design Consultant Contractor: Spectrum TechnoConsultants Pvt.Ltd
-
Contractor: AJAY KUMAR SHARMA CONTRACTOR
08
Naluchira Cable Stay Bridge,Kerala
-
Main Span - 75 + 150 + 75
-
Client Name:Kerala Infrastructure Investment FundBoard (KIIFB)
-
Contractor: Kurickal Developers LLP